Fire-resistant glazing: explained and simplified
Fire-rated glazing does not stop a fire. It buys time — time for people to get out, and time for the fire service to get in.
Fire-rated glazing does not stop a fire. It buys time — time for people to get out, and time for the fire service to get in.
Everything about it comes down to two things: how many minutes, and how much protection during those minutes. The number is the minutes. The letters are the protection.
The answer is usually on your drawings
Clients often ask us what rating they need. That decision belongs to the project's fire engineer and the authority having jurisdiction — but in most cases the answer is already on the drawings you hold.
- Fire strategy drawings mark compartment walls and fire barriers, usually colour-coded, with a period against them — 30, 60, 90 or 120 minutes.
- Door and window schedules should carry a period against every rated opening.
A glazed screen or door takes its requirement from the wall it sits in. Find the wall on the fire strategy drawing, read its period, and the opening follows from it.
Across the GCC it is common to see European, American and local civil defence conventions on the same project. A period on its own — “60 minutes” — does not say which system it belongs to. Both systems are set out below.
The letters — European (EN)
The element stays sealed. Flames and hot gases cannot pass through it. Assessed by cotton pad ignition, sustained flaming and gap gauges.
Stays cool to the touch Average temperature rise on the safe side limited to 140 °C, with no single point above 180 °C, so people and materials can be right beside it.
The number
The period follows the letters, in minutes — 30, 60, 90, 120 and beyond. So EI 60 means flame, smoke and heat all held back for 60 minutes. E 30 means flame and smoke only, for 30 minutes.
The period is a common yardstick measured under the standard furnace time–temperature curve of EN 1363-1. It is not a prediction of how a particular real fire will behave.
The American equivalent — UL, NFPA and ASTM
Anything rated over 20 minutes must also pass the hose stream test — the hot assembly is sprayed with a fire hose immediately after the furnace, applying thermal shock, impact and erosion at once. It removes products that survive the heat but shatter on contact with water.
“E ≈ fire-protective” and “EI ≈ fire-resistive” is useful shorthand, not an equivalence. The tests and criteria differ. Where a project cites both systems, each has to be evidenced separately.
The glass alone is never the rating
A fire rating belongs to a complete assembly, not to a pane of glass. It covers the glass, the frame, the beads, the intumescent seals, the gaskets, the hardware, the fixings, and how the whole thing is fixed into the surrounding wall.
- You cannot mix and match. Fire-resistive glass in a fire-protective frame gives you a fire-protective assembly. The weaker half sets the rating.
- The detail matters as much as the product. Change the glass, the bead, the seal, the size or the fixing centres, and the certification no longer describes what is on site.
This is also why the surrounding construction matters. A correctly built screen fixed into the wrong wall build-up, without proper perimeter firestopping, is not a rated installation.
The range at British Aluminium
We supply the complete range across both certification systems — EN and UL — as certified assemblies, not assembled from separately rated parts.
Aluminium and steel framed glazing, doors and public counters EN 1522 / EN 1063 · UL 752 / NIJ 0108.01 Acoustic systems 80 mm and 100 mm double-glazed partitions, acoustic doors and screens EN ISO 10140 / EN ISO 717-1 · ASTM E90 / E413 / E1332 Combined performance Fire with blast, ballistic with acoustic, and other multi-requirement assemblies Certified per configuration The easiest way to start: send us your fire strategy drawing and door and window schedule. We will read them, confirm what we understand the requirement to be, and identify which of our certified systems meets it.
Issued for information. Selection of fire ratings and of the building's compartmentation strategy is the responsibility of the project's fire engineer and the authority having jurisdiction. This document does not constitute fire engineering advice. Standards are cited as at the date shown and this guide is revised without notice; always work from the current issue.
The full guide
This page gives the text of our technical guide. The tables, charts and quick-reference sheet are in the PDF: download the full guide.
Related
Have a project requirement?
Send your drawings, specification and project location. Tell us what the opening needs to achieve and where you need support.